Construction activity resumed April 28 and continues until May 30 at the new Pinehurst Station.
Construction work is taking place at the new Pinehurst Station. Trains will share one track through the Shoreline South/148th Station requiring passengers to use the alternate side of the platform during construction hours. Work will take place evenings, Monday through Friday, from 7 p.m. until 5 a.m., and all day on Saturday and Sunday. Trains will arrive about every 12 minutes beginning at 5:30 p.m. Phase 1: March 24 through April 13 - Complete Phase 2: April 28 through May 30 - Trains will be using the Angle Lake platform. No work will be done May 10-11, May 17-18, and during the Memorial Day weekend of May 24-26